Page 49 - INCOLA EXCLUSIVE DATA CATALOGUE
P. 49

INCOLA Soundproof Piping Systems






                5.13 Points to take into consideration in installation of VESBO INCOLA
                      Soundproof Piping Systems


                Suggestions for Working in a Well-Organized Manner and in Compliance with the Rules


                •   Suitable working clothes should be used and the working area should be tidy.

                •   Implements should be picked according to the work.
                •   Necessary safety measures should be taken in working area.




                Criteria of Installation


                •   If the pipes need to be shortened, the pipe cutting process referred to in Section 5.2.1 must
                  be followed.
                •   No load should be placed on the pipe to prevent elliptical deformation on the pipe

                •   Pipes should be cut perpendicular to the pipe axis (90°).
                •   It should be checked after cutting, whether there is a fracture in the cut area.

                •   For easy assembly of cut ends, chamfering (15 °) should be done on the pipe ends.
                •   Burrs formed on the pipe ends after cutting should be taken with the burr cleaning apparatus
                  or snap blade knife referred to in Section 5.2.2.
                •   Muff and plug ends of pipes and fittings should be cleaned from dirt and oil.

                •   The connection parts should not be fully interconnected, and a 10 mm gap should be left in
                 between.

                •   The pipe fixing clamp should be fixed to the pipe just below the connection point in the
                  vertical line.
                •   The support clamp should be placed under the fixing clamp.

                •   Pipe support clamps should be used with a maximum interval of 2m for the safety of the
                 installation.

                •   A 5 meter high and “U” shaped leakage test device should be prepared.
                •   The system must pass the leakage test under 0.5 bar pressure for 15 minutes.